Michael Jordan Nissan – 013


003Glass installation is underway.  The front of the building is nearly complete.  Unfortunately, the final touches (ACM panels, louvers, and entry element) will not arrive for another 4-5 weeks.  The front of the building had to be close to complete before field measurements could be performed for factory fabrication of those elements could even begin.

On the inside, a large temporary partition was erected inside the existing Showroom.  The wall will remain in place for 5-6 weeks.  It has drastically changed the character of the space.  However, Michael Jordan Nissan is taking this opportunity to have some fun and will be adding decorations to create an “old-time used car lot” feel to the space.LED light fixtures also went up in Phase I.009

This project is being delivered through an Architect-led Design-Build process with Gontram Architecture and Ten Penny Construction, Inc.

LED light fixtures installed

LED light fixtures installed

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s