Interior sheetrock is underway.

Interior sheetrock is underway.

Mechanical mezzanine framed using light gauge metal framing.

Mechanical mezzanine framed using light gauge metal framing.

Sheetrock work is underway on the interior.  Exterior paint is also underway.  Still waiting for the ACM panels as they are still a few weeks away.

A mechanical mezzanine has been constructed, with mechanical equipment set.  Hopefully, we’ll have heat on later this week.

Sprinkler base piping has been installed.This coming week will entail completing the glass installation, ceiling grid installation, sprinkler drops, light fixture installation, exterior paint, and other work.

This project is being delivered through an Architect-led Design-Build process with Gontram Architecture and Ten Penny Construction, Inc.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s