Michael Jordan Nissan – 024


Underslab plumbing rough-in is complete

Underslab plumbing rough-in is complete

At Michael Jordan Nissan this week, the existing concrete slab was saw cut for underslab plumbing and electrical.  A new set of gang restrooms (ADA-compliant) is being installed as part of this phase.

Framing is also underway for new sales offices.

Wall framing underway.

Wall framing underway.

ACM panel installation continues on the two side canopies, and along the tricky transition between panel and ribbed block veneer.

ACM panel installation continues at canopies.

ACM panel installation continues at canopies.

This project is being delivered through an Architect-led Design-Build process with Gontram Architecture and Ten Penny Construction, Inc.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s