Michael Jordan Nissan – 030


In just a few more weeks, we will turn over the full, newly renovated and expanded Showroom for the Michael Jordan Nissan project in Durham, NC.

All above ceiling inspections are signed off.  Ceiling tile will be installed early next week.

Cleats and reveal material installed for wall panels

Cleats and reveal material installed for wall panels

Wall paneling in the Showroom will also go up.  This past week, final preparation took place to install wall cleats, reveal material, etc.

Last weekend, we began to replace the existing site lighting (500W metal halide) with CREE LED fixtures.  This will be a multi-phase replacement and will take a few weeks to complete given that we’re dealing with a working car dealership with lots of cars to move around.

New CREE fixture (foreground) and the existing metal halide fixtures (background)

New CREE fixture (foreground) and the existing metal halide fixtures (background)

This project is being delivered through an Architect-led Design-Build process with Gontram Architecture and Ten Penny Construction, Inc.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s