Sigma Nu – NCSU – 008


After topping out the masonry work last week, this week was spent preparing for the 1st floor concrete slab-on-grade.

Underslab waste plumbing ready for inspection

Underslab waste plumbing ready for inspection

Underslab plumbing is installed and was inspected today.

The waterproofing membrane for the concrete basement retaining wall is installed.  The drainage mat installation is underway.  The drainage mat will then be covered by board insulation and backfilled with stone.

Waterproofing and drainage mat installed.  Elevator and stair shafts in background.

Waterproofing and drainage mat installed. Elevator and stair shafts in background.

The concrete slab pour is scheduled for next Tuesday.  After that, structural steel is the next milestone!

For more information on the project, please check out our Website.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s