Michael Jordan Nissan – 038


Concrete slab patch and metal stud framing complete

Concrete slab patch and metal stud framing complete

This past week at Michael Jordan Nissan in Durham brought a lot of work not seen by the general public.  All work currently underway is back in the “belly” of the building, behind dust partitions and temporary walls.

Underslab plumbing and electrical rough-in’s were covered with concrete.  That allowed metal stud framing and sheetrock work to proceed.

Sheetrock installed

Sheetrock installed

On the 2nd floor, mechanical and electrical rough-in work was completed above ceiling.  Following that, the bolt-slot ceiling grid was installed along with the 2×4 LED light fixtures.

This project is being delivered through an Architect-led Design-Build process with Gontram Architecture and Ten Penny Construction, Inc.

Ceiling grid and LED fixtures installed

Ceiling grid and LED fixtures installed

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s