Framing is essentially complete on all 3 floors.  Wall sheathing installation is underway.

Framing is essentially complete on all 3 floors. Wall sheathing installation is underway.

Substantial progress was made this past week on the Sigma Nu fraternity house project at North Carolina State University. Weather was favorable all week (for once) which allowed the contractor to get a lot of framing work complete.

Wall framing was completed on the 3rd floor. With all strapping inspected, exterior wall sheathing installation was allowed to proceed.

Elevator rough-in proceeded along with plumbing wall and above-ceiling rough-in.

Roof trusses are due to arrive on Tuesday or Wednesday.

Front porch footings have been poured.  Steel columns await erection.

Front porch footings have been poured. Steel columns await erection.

For more information on the project, please check out our Website.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s