Sigma Nu – NCSU – 018


Another week of spotty weather at the Sigma Nu fraternity house project at North Carolina State University ended with a beautiful day and roof trusses being set.

Roof trusses swing above 3rd floor framing.

Roof trusses swing above 3rd floor framing.

By the end of next week, the roof should be sheathed and ready for roofing.  A weather barrier will be installed on the exterior walls ready for insulation and masonry.

Plumbing rough-in continues on the interior.  Both wall rough-in and above ceiling rough-in continued this past week.

For more information on the project, please check out our Website.

Roof trusses sorted and ready for lifting.

Roof trusses sorted and ready for lifting.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s