Interior finish work continues at the Sigma Nu Fraternity House at North Carolina State University.  Painting, wood trim, window frames, door frames, kitchen equipment, telecom raceway, ductwork, and lots of other work continues to push towards the December move-in date for Sigma Nu.

Ceiling framing under Rear Balcony

Ceiling framing under Rear Balcony

Panoramic in Officers Bedroom

Panoramic in Officers Bedroom

Kitchen Equipment fills the Kitchen

Kitchen Equipment fills the Kitchen

Temporary power should be connected today.  Gypcrete underlayment is scheduled for this weekend.

Once cable raceway installation is complete on the first and second floors, ceiling grid will be installed and above ceiling inspections obtained.  Once that happens, the interior will have a much more finished appearance.

Completion date is tentatively scheduled for mid-December of 2013.  For more information on the project, please check out our Website.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s