NC Retail Merchants Association – 003


NCRMA:  Steel is staged and ready for installation.

NCRMA: Steel is staged and ready for installation.

Demolition work for the interior renovation project for the NC Retail Merchants Association is complete.  This substantial project in downtown Raleigh, NC is transitioning from the demolition phase to the construction phase.

With demo complete, wall framing will begin this week.

Footings have been poured for new columns which will support the 1600 sq. ft. infill area of the 2nd floor.  Steel has been delivered and will be installed today and tomorrow.  Once installed, floor framing work will begin.

Construction is slated to be complete by June 30th.  Because of the accelerated schedule, the design-build process made the most sense to NCRMA.  Gontram Architecture and Ten Penny Construction have once again teamed up for this unique Design-Build opportunity.  As a single-source delivery method, we control budget and schedule, taking a lot of the usual Owner-associated worry out of the project.

Demolition is complete.

Demolition is complete.

NCRMA:  Steel delivery

NCRMA: Steel delivery

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s