NC Retail Merchants Association – 004


 

Wall framing underway below 2nd floor beams

Wall framing underway below 2nd floor beams

Interior wall and floor framing for the interior renovation project for the NC Retail Merchants Association is now underway.  This substantial project in downtown Raleigh, NC is beginning to take shape.

Interior walls on the 1st floor have been framed.

The steel beams for the 1600 sq. ft. infill area of the 2nd floor are in place.  Floor framing will be complete by Monday evening.

Construction is slated to be complete by June 30th.  Because of the accelerated schedule, the design-build process made the most sense to NCRMA.  Gontram Architecture and Ten Penny Construction have once again teamed up for this unique Design-Build opportunity.  As a single-source delivery method, we control budget and schedule, taking a lot of the usual Owner-associated worry out of the project.

Wall framing underway.

Wall framing underway.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s